As of the beginning of January 2024, general construction works on building №14: Earthworks, foundations – 100; Monolithic frame, walls and partitions – 100%; Internal engineering networks and elevators – 100%; Slot filling – 100%; Metal structures – 100%; Interior decoration and plates – 100%; Roof – 100%; Facades – 90% (painting of the facade […]
As of the beginning of December 2023, general construction works on building No. 14: Earthworks – 100%; Foundations – 100%; Monolithic frame, walls and partitions – 100%; Internal engineering networks: – arrangement of ventilation shafts and LCD – 100%; – water supply and sewerage – 95%; – heating per apartment – 90%; – electrical networks […]
As of the beginning of October 2023, general construction works on building No. 14: Earthworks – 100% Foundations – 100% Monolithic frame, walls and partitions – 100% Internal engineering networks: – arrangement of ventilation shafts and LCD – 100% -water supply and sewage – 75% – heating per apartment – 65% – electrical networks – […]
As of the beginning of September 2023, general construction works on building No. 14: Earthworks – 100%; Foundations – 100%; Monolithic frame, walls and partitions – 100%; Internal engineering networks: – arrangement of ventilation shafts and LCD – 100%; – water supply and sewerage – 55%; – apartment heating – 40%; – power grids – […]
As of the beginning of August 2023, general construction works on building №14: Earthworks and backfilling – 100% Foundations – 100% Waterproofing – 100% Monolithic frame – 100% Walls and partitions – 90% Internal engineering networks: – arrangement of ventilation shafts and LCD – 100% – power grids – 40% – sewerage – 40% – […]
As of the beginning of July 2023, general construction works on building №14: Earthworks– 100% Foundations – 100% Waterproofing – 100% Monolithic frame – 100% Walls and partitions – 80% Internal engineering networks: – arrangement of ventilation shafts and LCD – 100% – power grids – 30% Filling slots: – windows – 15% Decoration: plaster […]
As of June 2023, general construction works on building No. 14: Earthworks – 100%; Foundations – 100%; Monolithic frame – 100%; Walls and partitions – 65%; Internal engineering networks: – installation of ventilation shafts – 100%; – arrangement of LCD – 70%. On house #9: Earthworks, foundations – 100%; Monolithic frame, walls and partitions – […]
As of May 2023, general construction works on building №14: Earthworks – 70% Foundations – 100% Monolithic frame – 100% Walls and partitions – 45% Internal engineering networks: – installation of ventilation shafts – 85% – arrangement of LCD – 70% On house №9: Earthworks, foundations – 100% Monolithic frame, walls and partitions – 100% […]