Христина Чабан | Residential complex Kyivskyi
+38 (099) 255-90-46
uaroen
+38 (099) 255-90-46
Receive a consultation
+38 099 255 90 46
Receive a consultation
Христина Чабан

Archives

5% discount for servicemen and internally displaced persons

May 26, 2022

Everyone works on their own front. We believe in the victory of Ukraine and continue to work to provide citizens with comfortable and quality housing. We support our soldiers and all those who lost their homes in the fighting and were forced to change their place of residence.

Intergal-Bud has developed special offers for martial law * for the purchase of housing in the Western region (Lviv, MillTown, Chernivtsi, Kyiv, Kyiv, Zhytomyr, RiverCity) for servicemen, combatants and internally displaced persons. The promotional discount is 5% of the total cost of the apartment (for all methods of payment) and is provided with the appropriate documents.

The future is being built today!

Let’s rebuild the country together!

Martial law is currently in effect * until 23.08.22.

Resumption of construction work

May 19, 2022

At this time, it is very important to support each other with good news😌
We resumed work on the construction site of building №9 of the Kyivskyi residential complex. During martial law, this process is difficult, but despite this, the Intergal-Bud team believes in a stable future for our Ukraine with a developed infrastructure and reliable buildings.
The future is being built today!
We are waiting for you at the address: Mizyuna Street, 20.
Tel .: +380501024455
Together to victory❤️🇺🇦

House №8 in the residential complex “Kyivskyi” was put into operation

May 16, 2022

We have great news, for the first time since the beginning of large-scale military operations, the Intergal-Bud facility received a certificate of commissioning. It became the building №8 of the residential complex “Kyivsky” in Chernivtsi.
We are waiting for you from Monday to Friday from 10:00 to 16:00 (Saturday from 10:00 to 15:00 by appointment) at: Mizyuna Street, 20.
Tel .: +380501024455

The course of construction for February 2022

February 8, 2022

As of 01.02.2022, the installation of an in-house gas pipeline and a gas metering unit is underway at house № 8.

House №9:

1. Earthworks – 100%
2. The foundation of the house – 100%
3. The foundation of the tower crane – 100%
4. Frame of the building – 35%
5. Waterproofing of the bases – 85%
6. Brickwork – 25%
7. Internal engineering networks:
-Installation of ventilation shafts – 10%
– Device SKD – 10%

House №14:
1. Earthworks – 70%
2. The foundation of the house – 100%
3. The foundation of the tower crane – 100%
4. Frame of the building – 5%
5. Waterproofing of the bases – 35%
6. Brickwork – 5%

Construction progress for January 2022

January 14, 2022

As of the beginning of January, the following general construction works have been carried out on house №8:

1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 95%
– Plumbing work – 100%
– Heating – 100%
– Intercom – 95%
8. Finishing works:
– plastering of walls – 100%
– floor screeds – 100%
– plastering of ceilings – 95%
– tiling – 75%
– wall decoration (decorative plaster) – 65%
9. Window constructions – 100%
10. Door constructions – 100%
11. Metal structures – 85%
12. Roof – 100%
13. Facade – 90%
14. Elevators – 95%
15. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 100%
16. Landscaping – 80%
17. Playgrounds – 95%
House №9:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Frame of the building – 30%
5. Waterproofing of foundations – 80%
6. Brickwork – 15%
House №14:
1. Earthworks – 70%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Frame of the building – 5%
5. Waterproofing of foundations – 5%

Progress of construction in December 2021

January 14, 2022

As of the beginning of December, the following general construction works have been carried out on house №8:

1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 75%
– Plumbing works – 85%
– Heating – 75%
– Intercom – 90%
8. Finishing works:
– plastering of walls – 95%
– floor screeds – 75%
– plastering of ceilings – 50%
– tiling – 35%
9. Window constructions – 100%
10. Door constructions – 60%
11. Metal structures – 70%
12. Roof – 95%
13. Facade – 85%
14. Elevators – 95%
15. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 100%
16. Landscaping – 70%

House №9:
1. Earthworks – 85%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Frame of the building – 15%
5. Waterproofing of foundations – 60%
6. Brickwork – 5%

House №14:
1. Earthworks – 65%
2. The foundation of the house – 50%
3. Tower crane foundation – 100%

The course of construction for November 2021

November 3, 2021

As of the beginning of November, the following general construction works have been carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Building frame – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 70%
– Plumbing – 75%
– Heating – 50%
– Intercom – 70%
8. Finishing works:
– plastering of walls – 70%
– floor screeds – 25%
– plastering of ceilings – 10%
9. Window constructions – 100%
10. Metal structures – 60%
11. Roof – 85%
12. Facade – 70%
13. Elevators – 95%
14. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– external lighting – 100%
15. Landscaping – 35%
House №9:
1. Earthworks – 75%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Building frame – 10%
5. Waterproofing of the bases – 30%

The course of construction for October 2021

October 4, 2021

As of the beginning of October, the following general construction works were carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 60%
– Plumbing – 70%
– Heating – 40%
– Intercom – 50%
8. Finishing works:
– plastering of walls – 40%
9. Window constructions – 95%
10. Metal constructions – 30%
11. Roof – 85%
12. Facade – 35%
13. Elevators – 95%
14. External engineering networks :
– electricity supply – 80%
– sewerage – 95%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 50%
15. Landscaping – 5%
House № 9:
1. Earthworks – 70%
2. The foundation of the house is 70%
3. Frame of the building – 5%

The course of construction for September 2021

September 1, 2021

As of the beginning of September, the following general construction works have been carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Building frame – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 95%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 95%
– Electrical work – 50%
– Plumbing work – 60 %
– Heating – 25%
– Intercom – 30%
8. Finishing works:
– plastering of walls – 20%
9. Window constructions – 95%
10. Metal structures – 25%
11. Roof – 50%
12. Facade – 5%
13. Elevators – 10%
14. External engineering networks:
– electricity supply – 50%
– sewerage – 80%
– water supply – 80%
– gas supply – 50%

The course of construction for August 2021

August 3, 2021

As of the beginning of August, the following general construction works were carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. The foundation of the tower crane is 100%
4. The frame of the building is 100%
5. Waterproofing of the bases – 100%
6. Brickwork – 75%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 95%
– Electrical works – 20%
– Plumbing works – 25%
8. Window constructions – 65%
9. Roof – 20%
10. External engineering networks:
– electricity supply – 50%
– sewerage – 50%