The “Intergal-Bud” company welcomes the state initiative, which is designed to make the purchase of residential real estate with a mortgage more affordable for Ukrainians, and joins the program. From now on, you can choose an apartment for purchase as part of “eOselya” in “Kyivskyi” residential complex
Every year on Builder’s Day, August 14, the “Intergal-Bud” company celebrates its birthday. This year — on the nineteenth.
Despite everything, we have reason to be proud. The company “Intergal-Bud” was and remains the leader of the construction market of Ukraine. Even in extremely difficult circumstances, we continue to work and provide Ukrainians with modern and high-quality housing.
During these 19 years, we implemented many projects, realized the dream of owning apartments for more than 19 thousand families, won many industry awards and were repeatedly recognized as the best developer. And most importantly, we have gained the reputation of one of the most reliable developers, with no unfinished business in its portfolio.
Now, when the country has been engulfed in war, we are holding our front – the construction front. We work tirelessly to build the future of Ukraine. And this future will be peaceful.
Everything will be Ukraine!
We can’t wait any longer to share some great news with you☺️
Therefore, the @intergal_bud team is pleased to announce the start of the sale of house No. 14 in the “Kyivskyi” residential complex, at the address of st. Mizyuna, 20.
▪️Location in a quiet area of Chernivtsi.
▪️Developed infrastructure.
▪️ Convenient transport junction.
▪️Awe-inspiring architecture.
▪️High quality construction.
📞Don’t delay, our managers are looking forward to your calls: +38 (099) 255-90-46
But in the sales department, which is located next to the “Kyivskyi” residential complex.
At this time, it is very important to support each other with good news😌
We resumed work on the construction site of building №9 of the Kyivskyi residential complex. During martial law, this process is difficult, but despite this, the Intergal-Bud team believes in a stable future for our Ukraine with a developed infrastructure and reliable buildings.
The future is being built today!
We are waiting for you at the address: Mizyuna Street, 20.
Tel .: +380501024455
Together to victory❤️🇺🇦
We have great news, for the first time since the beginning of large-scale military operations, the Intergal-Bud facility received a certificate of commissioning. It became the building №8 of the residential complex “Kyivsky” in Chernivtsi.
We are waiting for you from Monday to Friday from 10:00 to 16:00 (Saturday from 10:00 to 15:00 by appointment) at: Mizyuna Street, 20.
Tel .: +380501024455
As of 01.02.2022, the installation of an in-house gas pipeline and a gas metering unit is underway at house № 8.
House №9:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. The foundation of the tower crane – 100%
4. Frame of the building – 35%
5. Waterproofing of the bases – 85%
6. Brickwork – 25%
7. Internal engineering networks:
-Installation of ventilation shafts – 10%
– Device SKD – 10%
House №14:
1. Earthworks – 70%
2. The foundation of the house – 100%
3. The foundation of the tower crane – 100%
4. Frame of the building – 5%
5. Waterproofing of the bases – 35%
6. Brickwork – 5%
As of the beginning of January, the following general construction works have been carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 95%
– Plumbing work – 100%
– Heating – 100%
– Intercom – 95%
8. Finishing works:
– plastering of walls – 100%
– floor screeds – 100%
– plastering of ceilings – 95%
– tiling – 75%
– wall decoration (decorative plaster) – 65%
9. Window constructions – 100%
10. Door constructions – 100%
11. Metal structures – 85%
12. Roof – 100%
13. Facade – 90%
14. Elevators – 95%
15. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 100%
16. Landscaping – 80%
17. Playgrounds – 95%
House №9:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Frame of the building – 30%
5. Waterproofing of foundations – 80%
6. Brickwork – 15%
House №14:
1. Earthworks – 70%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Frame of the building – 5%
5. Waterproofing of foundations – 5%
As of the beginning of December, the following general construction works have been carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 75%
– Plumbing works – 85%
– Heating – 75%
– Intercom – 90%
8. Finishing works:
– plastering of walls – 95%
– floor screeds – 75%
– plastering of ceilings – 50%
– tiling – 35%
9. Window constructions – 100%
10. Door constructions – 60%
11. Metal structures – 70%
12. Roof – 95%
13. Facade – 85%
14. Elevators – 95%
15. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 100%
16. Landscaping – 70%
House №9:
1. Earthworks – 85%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Frame of the building – 15%
5. Waterproofing of foundations – 60%
6. Brickwork – 5%
House №14:
1. Earthworks – 65%
2. The foundation of the house – 50%
3. Tower crane foundation – 100%
As of the beginning of November, the following general construction works have been carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Building frame – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 70%
– Plumbing – 75%
– Heating – 50%
– Intercom – 70%
8. Finishing works:
– plastering of walls – 70%
– floor screeds – 25%
– plastering of ceilings – 10%
9. Window constructions – 100%
10. Metal structures – 60%
11. Roof – 85%
12. Facade – 70%
13. Elevators – 95%
14. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– external lighting – 100%
15. Landscaping – 35%
House №9:
1. Earthworks – 75%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Building frame – 10%
5. Waterproofing of the bases – 30%
As of the beginning of October, the following general construction works were carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 60%
– Plumbing – 70%
– Heating – 40%
– Intercom – 50%
8. Finishing works:
– plastering of walls – 40%
9. Window constructions – 95%
10. Metal constructions – 30%
11. Roof – 85%
12. Facade – 35%
13. Elevators – 95%
14. External engineering networks :
– electricity supply – 80%
– sewerage – 95%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 50%
15. Landscaping – 5%
House № 9:
1. Earthworks – 70%
2. The foundation of the house is 70%
3. Frame of the building – 5%