At the beginning of April, the following general construction works were performed on the house №8: 1. Earthworks – 95% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 35% 5. Waterproofing of foundations – 100% 6. Brickwork – 15% 7. Internal engineering […]