Shopping Center Monolithic works completed Wall masonry on the 1st floor is in progress Installation of glazing systems is underway Roofing works are being performed Installation of external and internal engineering networks is ongoing Building 10 Foundation slab for sections 1 and 2 is being installed Concrete base under sections 3, 4, and 5 has […]
Shopping CenterMonolithic works have been completedWall masonry on the 1st floor is in progressInstallation of façade glazing systems is underwayRoofing works are ongoingInstallation of external and internal utility networks is in progress Building 10Foundation slab installation is underway for sections 1 and 2Concrete preparation has been completed for sections 3, 4, and 5Concrete preparation for […]
Shopping Center: Roof slab reinforcement is being completed.Formwork installation for the stairwell walls is in progress.Ventilation ducts on the roof are being built.Metal structures for stained glass windows are being installed.Installation of external water supply and sewage networks is underway. Building 10: Excavation work for the underground parking area is in progress.Concrete foundation preparation under […]
Shopping Center: Reinforcement of columns on the 1st floor is in progress. Slab reinforcement on the roof (1st section) is underway. Wall masonry with aerated concrete blocks is being carried out on the 1st floor. Building 10: Excavation work is in progress for sections 1 and 2. Sub-base concrete work for sections 3, 4, and […]
Installation of floor formwork above commercial premises Formwork is installed to fill the floor slab, which will become the basis between the floors. Masonry of walls in the parking lot The construction of the walls in the underground parking is carried out using high-quality materials that ensure the durability of the structure. Waterproofing of the […]
Works as of the beginning of May: House No. 14: Land improvement works – 95% (paving of sidewalks and arrangement of green areas are being completed). Shopping center: Earthworks – works on the development of the pit have been completed; Construction of the foundation is completed; Arrangement of the frame – 10% (work is being […]
Works as of the beginning of April: House No. 14: Works on the improvement of the territory – 65% (paving works on sidewalks and driveways are being carried out). Shopping center: Earthworks – works on the development of the pit have been completed; Crushed stone preparation – completed; Concrete preparation – completed; Foundation plate – […]