Works as of the beginning of April:
House No. 14:
Works on the improvement of the territory – 65% (paving works on sidewalks and driveways are being carried out).
Shopping center:
Earthworks – works on the development of the pit have been completed;
Crushed stone preparation – completed;
Concrete preparation – completed;
Foundation plate – 70%.





