Shopping Center
Monolithic works completed
Wall masonry on the 1st floor is in progress
Installation of glazing systems is underway
Roofing works are being performed
Installation of external and internal engineering networks is ongoing
Building 10
Foundation slab for sections 1 and 2 is being installed
Concrete base under sections 3, 4, and 5 has been completed
Concrete base preparation for the parking area is in progress