Construction progress for October 2020

We continue to share with you the news from the construction site of the residential area “Kyivsky”for October 2020.

The following works were performed on the house number 7: ⠀
-Installation of the floor slab of the seventh floor in section 2; 3.
-Attachment of walls and columns of the fifth floor on 1 section.
-Installation of brick walls on the third and fourth floors of 2, 3 sections.
-Installation of smoke and ventilation ducts.