As of the beginning of September 2023, general construction works on building No. 14:
Earthworks – 100%;
Foundations – 100%;
Monolithic frame, walls and partitions – 100%;
Internal engineering networks:
– arrangement of ventilation shafts and LCD – 100%;
– water supply and sewerage – 55%;
– apartment heating – 40%;
– power grids – 55%;
– low current networks – 60%;
Filling slots:
– 70% of the windows of the apartment building;
Metal structures – 20%;
Decoration:
– plaster – 60%;
Roof – 90%;
Facades – 25%;
External engineering networks:
– sewerage – 40%.