Construction progress in February 2025 | Residential complex Kyivskyi

Shopping Center:

  • Reinforcement of columns on the 1st floor is in progress.
  • Slab reinforcement on the roof (1st section) is underway.
  • Wall masonry with aerated concrete blocks is being carried out on the 1st floor.

Building 10:

  • Excavation work is in progress for sections 1 and 2.
  • Sub-base concrete work for sections 3, 4, and 5 has been completed.