Works as of the beginning of April: House No. 14: Works on the improvement of the territory – 65% (paving works on sidewalks and driveways are being carried out). Shopping center: Earthworks – works on the development of the pit have been completed; Crushed stone preparation – completed; Concrete preparation – completed; Foundation plate – […]
At the beginning of April, the following general construction works were performed on the house №8: 1. Earthworks – 95% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 35% 5. Waterproofing of foundations – 100% 6. Brickwork – 15% 7. Internal engineering […]