General construction works as of February 2, 2021: House №8 1. Earthworks – 80% (works are underway) 2. Tower crane foundation – 100% (completed) 3. Frame of the building – 10% (work is underway) 4. Waterproofing of the bases – 50% (works are conducted) House №7 1. Brickwork – 85% (work in progress) 2. Window […]