As of the beginning of January, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 100% 7. […]