January | | Residential complex Kyivskyi

As of the beginning of February 2024, general construction work on building #14 was completed

Read more

As of the beginning of January 2024, general construction works on building №14: Earthworks, foundations – 100; Monolithic frame, walls and partitions – 100%; Internal engineering networks and elevators – 100%; Slot filling – 100%; Metal structures – 100%; Interior decoration and plates – 100%; Roof – 100%; Facades – 90% (painting of the facade […]

Read more

As of the beginning of January, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 100% 7. […]

Read more