As of June 2023, general construction works on building No. 14: Earthworks – 100%; Foundations – 100%; Monolithic frame – 100%; Walls and partitions – 65%; Internal engineering networks: – installation of ventilation shafts – 100%; – arrangement of LCD – 70%. On house #9: Earthworks, foundations – 100%; Monolithic frame, walls and partitions – […]