General construction works as of March 2, 2021: House №8 1. Earthworks – 80% (works are underway) 2. Frame of the building – 15% (work is underway) 3. Waterproofing of the bases – 50% (works are conducted) 4. Brickwork -5% (work is underway) House №7 1. Window constructions – 95% (works are underway) 2. Internal […]