september | | Residential complex Kyivskyi

As of the beginning of September 2023, general construction works on building No. 14: Earthworks – 100%; Foundations – 100%; Monolithic frame, walls and partitions – 100%; Internal engineering networks: – arrangement of ventilation shafts and LCD – 100%; – water supply and sewerage – 55%; – apartment heating – 40%; – power grids – […]

Read more

As of the beginning of September, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house is 100% 3. Tower crane foundation – 100% 4. Building frame – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 95% 7. Internal engineering networks: […]

Read more