As of the beginning of September, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house is 100% 3. Tower crane foundation – 100% 4. Building frame – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 95% 7. Internal engineering networks: […]

Read more

As of the beginning of August, the following general construction works were carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house is 100% 3. The foundation of the tower crane is 100% 4. The frame of the building is 100% 5. Waterproofing of the bases – 100% 6. Brickwork […]

Read more

As of the beginning of July, the following general construction works have been carried out on house №8: 1. Earthworks – 100% (completed) 2. The foundation of the house – 100% (completed) 3. Tower crane foundation – 100% (completed) 4. Frame of the building – 100% (completed) 5. Waterproofing of foundations – 100% (completed) 6. […]

Read more

At the beginning of June, the following general construction works were performed on the house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 85% 5. Waterproofing of foundations – 100% 6. Brickwork – 50% 7. Internal engineering […]

Read more

At the beginning of May, the following works were performed on the house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 65% 5. Waterproofing of foundations – 100% 6. Brickwork – 30% 7. Internal engineering networks: – […]

Read more

At the beginning of April, the following general construction works were performed on the house №8: 1. Earthworks – 95% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 35% 5. Waterproofing of foundations – 100% 6. Brickwork – 15% 7. Internal engineering […]

Read more

We would like to draw your attention to the fact that in connection with the holiday of March 8, our sales department works according to the changed work schedule: March 5 from 10:00 to 16:00 March 6 from 10:00 to 15:00 March 7 is a day off March 8 from 10:00 to 15:00 In all […]

Read more

General construction works as of March 2, 2021: House №8 1. Earthworks – 80% (works are underway) 2. Frame of the building – 15% (work is underway) 3. Waterproofing of the bases – 50% (works are conducted) 4. Brickwork -5% (work is underway) House №7 1. Window constructions – 95% (works are underway) 2. Internal […]

Read more

General construction works as of February 2, 2021: House №8 1. Earthworks – 80% (works are underway) 2. Tower crane foundation – 100% (completed) 3. Frame of the building – 10% (work is underway) 4. Waterproofing of the bases – 50% (works are conducted) House №7 1. Brickwork – 85% (work in progress) 2. Window […]

Read more

Until February 28, 2021, there are especially attractive winter discounts – up to UAH 570 per m2. Therefore, we recommend that you take this opportunity to visit our sales department. After all, this is where the boldest dreams come true. New Year’s Eve is a time for dreams and their realization! Therefore, boldly dream of […]