As of the beginning of September, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house is 100% 3. Tower crane foundation – 100% 4. Building frame – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 95% 7. Internal engineering networks: […]
As of the beginning of July, the following general construction works have been carried out on house №8: 1. Earthworks – 100% (completed) 2. The foundation of the house – 100% (completed) 3. Tower crane foundation – 100% (completed) 4. Frame of the building – 100% (completed) 5. Waterproofing of foundations – 100% (completed) 6. […]
At the beginning of June, the following general construction works were performed on the house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 85% 5. Waterproofing of foundations – 100% 6. Brickwork – 50% 7. Internal engineering […]
At the beginning of May, the following works were performed on the house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 65% 5. Waterproofing of foundations – 100% 6. Brickwork – 30% 7. Internal engineering networks: – […]
At the beginning of April, the following general construction works were performed on the house №8: 1. Earthworks – 95% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 35% 5. Waterproofing of foundations – 100% 6. Brickwork – 15% 7. Internal engineering […]
General construction works as of March 2, 2021: House №8 1. Earthworks – 80% (works are underway) 2. Frame of the building – 15% (work is underway) 3. Waterproofing of the bases – 50% (works are conducted) 4. Brickwork -5% (work is underway) House №7 1. Window constructions – 95% (works are underway) 2. Internal […]
General construction works as of February 2, 2021: House №8 1. Earthworks – 80% (works are underway) 2. Tower crane foundation – 100% (completed) 3. Frame of the building – 10% (work is underway) 4. Waterproofing of the bases – 50% (works are conducted) House №7 1. Brickwork – 85% (work in progress) 2. Window […]
Until February 28, 2021, there are especially attractive winter discounts – up to UAH 570 per m2. Therefore, we recommend that you take this opportunity to visit our sales department. After all, this is where the boldest dreams come true. New Year’s Eve is a time for dreams and their realization! Therefore, boldly dream of […]