Construction progress for December 2020

We continue to share with you the news from the construction site of the residential district “Kyiv”
The following works were performed on the house number 8 at the beginning of December:
1. Earthworks – 50% (works are underway)
2. The foundation of the house – 50% (work is underway)
3. Tower crane foundation – 100% (completed)

House №7:
1. Brickwork – 55% (work in progress)
2. Window constructions – 35% (works are underway)
3. Internal engineering networks
– Installation of ventilation shafts – 100% (completed)
– SKD installation – 95% (works are underway)
– Electrical work – 20% (work in progress)
– Plumbing works – 20% (works are underway)
4. Roof – 30% (work in progress)