As of the beginning of January, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 100% 7. […]
As of the beginning of December, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 100% 7. […]
As of the beginning of November, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house is 100% 3. Tower crane foundation – 100% 4. Building frame – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 100% 7. Internal engineering networks: […]
As of the beginning of October, the following general construction works were carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house is 100% 3. Tower crane foundation – 100% 4. Frame of the building – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 100% 7. Internal engineering […]
As of the beginning of September, the following general construction works have been carried out on house №8: 1. Earthworks – 100% 2. The foundation of the house is 100% 3. Tower crane foundation – 100% 4. Building frame – 100% 5. Waterproofing of foundations – 100% 6. Brickwork – 95% 7. Internal engineering networks: […]
As of the beginning of July, the following general construction works have been carried out on house №8: 1. Earthworks – 100% (completed) 2. The foundation of the house – 100% (completed) 3. Tower crane foundation – 100% (completed) 4. Frame of the building – 100% (completed) 5. Waterproofing of foundations – 100% (completed) 6. […]
At the beginning of June, the following general construction works were performed on the house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 85% 5. Waterproofing of foundations – 100% 6. Brickwork – 50% 7. Internal engineering […]
At the beginning of May, the following works were performed on the house №8: 1. Earthworks – 100% 2. The foundation of the house – 100% 3. Tower crane foundation – 100% 4. The frame of the building – 65% 5. Waterproofing of foundations – 100% 6. Brickwork – 30% 7. Internal engineering networks: – […]