As of the beginning of January 2024, general construction works on building №14:
Earthworks, foundations – 100;
Monolithic frame, walls and partitions – 100%;
Internal engineering networks and elevators – 100%;
Slot filling – 100%;
Metal structures – 100%;
Interior decoration and plates – 100%;
Roof – 100%;
Facades – 90% (painting of the facade of section 3-4 and decoration of the basement part of the building is being completed).