Construction progress for December 2023 | Residential complex Kyivskyi

As of the beginning of December 2023, general construction works on building No. 14:

Earthworks – 100%;
Foundations – 100%;
Monolithic frame, walls and partitions – 100%;
Internal engineering networks:
– arrangement of ventilation shafts and LCD – 100%;
– water supply and sewerage – 95%;
– heating per apartment – 90%;
– electrical networks – 90%;
– low-current networks – 95%;
Filling slots:
– windows m/p – 100%;
– apartment doors – 90%;
– technical doors and hatches – 70%;
Elevators – 95%;
Metal structures – 80%;
Decoration:
-plaster and screed – 100%;
– tiling floors – 70%;
– plastering of ceilings – 80%;
Roof – 100%;
Facades – 70%;
External engineering networks – 100%.