Construction progress for October 2023 | Residential complex Kyivskyi

As of the beginning of October 2023, general construction works on building No. 14:
Earthworks – 100%
Foundations – 100%
Monolithic frame, walls and partitions – 100%
Internal engineering networks:
– arrangement of ventilation shafts and LCD – 100%
-water supply and sewage – 75%
– heating per apartment – 65%
– electrical networks – 65%
– low-current networks – 90%
Filling slots:
– windows m/p – 95%
– Elevators – 50%
-Metal structures – 10%
Decoration:
-plaster – 80%
– screed – 45%
– tiling floors – 25%
– plastering of ceilings – 40%
Roof – 100%
Facades – 45%
External engineering networks:
-sewerage – 70%
– water supply – 100%