As of the beginning of July 2023, general construction works on building №14:
Earthworks– 100%
Foundations – 100%
Waterproofing – 100%
Monolithic frame – 100%
Walls and partitions – 80%
Internal engineering networks:
– arrangement of ventilation shafts and LCD – 100%
– power grids – 30%
Filling slots:
– windows – 15%
Decoration:
plaster – 10%