Construction progress for August 2023 | Residential complex Kyivskyi

As of the beginning of August 2023, general construction works on building №14:

Earthworks and backfilling – 100%
Foundations – 100%
Waterproofing – 100%
Monolithic frame – 100%
Walls and partitions – 90%
Internal engineering networks:
– arrangement of ventilation shafts and LCD – 100%
– power grids – 40%
– sewerage – 40%
– low current networks – 30%
Filling slots:
– windows m/p – 45%
Decoration:
– plaster – 35%
Roof – 30%