As of June 2023, general construction works on building No. 14:
Earthworks – 100%;
Foundations – 100%;
Monolithic frame – 100%;
Walls and partitions – 65%;
Internal engineering networks:
– installation of ventilation shafts – 100%;
– arrangement of LCD – 70%.
On house #9:
Earthworks, foundations – 100%;
Monolithic frame, walls and partitions – 100%;
Internal engineering networks:
– water supply and sewerage – 90%;
– heating per apartment – 90%;
– power grids – 95%;
– low current networks – 100%;
Filling slots:
– windows of m/p – 100%;
– apartment doors – 100%;
– technical doors and hatches – 90%;
Elevators – 100%;
Metal structures – 60%;
Roof – 100%;
Facades – 75%;
Decoration:
– plaster and screed – 100%;
– wall decoration – 70%;
– tiling floors – 85%;
External engineering networks:
– electricity supply – 100%;
– sewerage – 100%;
– water supply – 100%;
Landscaping – 40%.