Construction progress for May 2023

As of May 2023, general construction works on building №14:
Earthworks – 70%
Foundations – 100%
Monolithic frame – 100%
Walls and partitions – 45%
Internal engineering networks:
– installation of ventilation shafts – 85%
– arrangement of LCD – 70%

On house №9:
Earthworks, foundations – 100%
Monolithic frame, walls and partitions – 100%
Internal engineering networks:
– water supply and sewage – 85%
– apartment heating – 80%
– power grids – 90%
– low current networks – 100%
Filling slots:
– windows of m/p – 100%
– apartment doors – 100%
– technical doors and hatches – 90%
Elevators – 100%
Roof – 100%
Facades – 50%
Decoration:
– plaster and screed – 100%
– wall decoration – 20%
– tiling floors – 65%
External engineering networks:
– electricity supply – 90%
– sewerage – 85%
– water supply – 100%