We continue to share with you the news from the construction site of the residential area “Kyivsky”
⠀
At the beginning of November, the following works were performed on house number 7:
1. Earthworks – 100% (completed)
2. The foundation of the house – 100% (completed)
3. Tower crane foundation – 100% (completed)
4. Waterproofing of foundations – 100% (completed)
5. Frame of the building – 95% (work is underway)
6. Brickwork – 40% (work in progress)
7. Installation of ventilation shafts – 60% (work is underway)
8. Installation of SKD – 60% (works are underway)
9. Window constructions – 25% (works are underway)