As of 01.02.2022, the installation of an in-house gas pipeline and a gas metering unit is underway at house № 8.
House №9:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. The foundation of the tower crane – 100%
4. Frame of the building – 35%
5. Waterproofing of the bases – 85%
6. Brickwork – 25%
7. Internal engineering networks:
-Installation of ventilation shafts – 10%
– Device SKD – 10%
House №14:
1. Earthworks – 70%
2. The foundation of the house – 100%
3. The foundation of the tower crane – 100%
4. Frame of the building – 5%
5. Waterproofing of the bases – 35%
6. Brickwork – 5%