Works as of the beginning of May:
House No. 14:
Land improvement works – 95% (paving of sidewalks and arrangement of green areas are being completed).
Shopping center:
Earthworks – works on the development of the pit have been completed;
Construction of the foundation is completed;
Arrangement of the frame – 10% (work is being carried out on the vertical structures of the parking lot).