At the beginning of April, the following general construction works were performed on the house №8:
1. Earthworks – 95%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 35%
5. Waterproofing of foundations – 100%
6. Brickwork – 15%
7. Internal engineering networks:
– Installation of ventilation shafts – 10%
– Device SKD – 10%
At the beginning of April, the following general construction works were performed on the house №7:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Waterproofing of foundations – 100%
5. The frame of the building – 100%
6. Brickwork – 100%
7. Window constructions – 95%
8. Internal engineering networks:
– Installation of ventilation shafts – 100%
– SKD installation – 100%
– Electrical work – 60%
– Plumbing works – 80%
– Heating – 70%
– Intercom – 70%
9. Finishing works:
– plastering of walls – 100%
– floor screeds – 70%
– ceiling plastering – 40%
– tile finishing – 20%
10. Door constructions – 30%
11. Roof – 80%
12. Facade – 40%
13. Metal structures – 50%
14. Elevators – 60%
15. External engineering networks:
– power supply – 80%
– sewerage – 90%
– water supply – 90%
– gas supply – 30%
16. Landscaping – 20%