The course of construction for May 2021⠀

At the beginning of May, the following works were performed on the house №8:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 65%
5. Waterproofing of foundations – 100%
6. Brickwork – 30%
7. Internal engineering networks:
– Installation of ventilation shafts – 25%
– Device SKD – 25%

House №7:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Waterproofing of foundations – 100%
5. The frame of the building – 100%
6. Brickwork – 100%
7. Window constructions – 95%
8. Internal engineering networks:
– Installation of ventilation shafts – 100%
– SKD installation – 100%
– Electrical work – 80%
– Plumbing work – 90%
– Heating – 90%
– Intercom – 95%
– Gas supply – 5%
9. Finishing works:
– plastering of walls – 100%
– floor screeds – 100%
– ceiling plastering – 70%
– finishing with tiles – 80%
– wall decoration (decorative plaster) – 40%
10. Door constructions – 95%
11. Roof – 95%
12. Facade – 60%
13. Metal structures – 60%
14. Elevators – 95%
15. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 90%
16. Landscaping – 60%