At the beginning of June, the following general construction works were performed on the house №8:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 85%
5. Waterproofing of foundations – 100%
6. Brickwork – 50%
7. Internal engineering networks:
– Installation of ventilation shafts – 50%
– Device SKD – 50%
House №7:
1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Waterproofing of foundations – 100%
5. The frame of the building – 100%
6. Brickwork – 100%
7. Window constructions – 100%
8. Internal engineering networks:
– installation of ventilation shafts – 100%
– SKD installation – 100%
– electrical work – 100%
– plumbing work – 100%
– heating – 100%
– intercom – 100%
– gas supply – 30%
9. Finishing works:
– plastering of walls – 100%
– floor screeds – 100%
– ceiling plastering – 95%
– finishing with tiles – 95%
– wall decoration (decorative plaster) – 95%
10. Door constructions – 100%
11. Roof – 95%
12. Facade – 95%
13. Metal structures – 80%
14. Elevators – 100%
15. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 100%
16. Landscaping – 75%