As of the beginning of July, the following general construction works have been carried out on house №8:
1. Earthworks – 100% (completed)
2. The foundation of the house – 100% (completed)
3. Tower crane foundation – 100% (completed)
4. Frame of the building – 100% (completed)
5. Waterproofing of foundations – 100% (completed)
6. Brickwork – 55% (work in progress)
7. Internal engineering networks:
– Installation of ventilation shafts – 75% (work in progress)
– SKD installation – 75% (works are underway)
8. Window constructions – 25% (works are underway)
House №7:
General construction works on house №7 have been completed