As of the beginning of August, the following general construction works were carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. The foundation of the tower crane is 100%
4. The frame of the building is 100%
5. Waterproofing of the bases – 100%
6. Brickwork – 75%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 95%
– Electrical works – 20%
– Plumbing works – 25%
8. Window constructions – 65%
9. Roof – 20%
10. External engineering networks:
– electricity supply – 50%
– sewerage – 50%