The course of construction for September 2021

As of the beginning of September, the following general construction works have been carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Building frame – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 95%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 95%
– Electrical work – 50%
– Plumbing work – 60 %
– Heating – 25%
– Intercom – 30%
8. Finishing works:
– plastering of walls – 20%
9. Window constructions – 95%
10. Metal structures – 25%
11. Roof – 50%
12. Facade – 5%
13. Elevators – 10%
14. External engineering networks:
– electricity supply – 50%
– sewerage – 80%
– water supply – 80%
– gas supply – 50%