The course of construction for October 2021

As of the beginning of October, the following general construction works were carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 60%
– Plumbing – 70%
– Heating – 40%
– Intercom – 50%
8. Finishing works:
– plastering of walls – 40%
9. Window constructions – 95%
10. Metal constructions – 30%
11. Roof – 85%
12. Facade – 35%
13. Elevators – 95%
14. External engineering networks :
– electricity supply – 80%
– sewerage – 95%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 50%
15. Landscaping – 5%
House № 9:
1. Earthworks – 70%
2. The foundation of the house is 70%
3. Frame of the building – 5%