As of the beginning of November, the following general construction works have been carried out on house №8:
1. Earthworks – 100%
2. The foundation of the house is 100%
3. Tower crane foundation – 100%
4. Building frame – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 70%
– Plumbing – 75%
– Heating – 50%
– Intercom – 70%
8. Finishing works:
– plastering of walls – 70%
– floor screeds – 25%
– plastering of ceilings – 10%
9. Window constructions – 100%
10. Metal structures – 60%
11. Roof – 85%
12. Facade – 70%
13. Elevators – 95%
14. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– external lighting – 100%
15. Landscaping – 35%
House №9:
1. Earthworks – 75%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Building frame – 10%
5. Waterproofing of the bases – 30%