Progress of construction in December 2021 | Residential complex Kyivskyi
+38 (099) 255-90-46
uaroen
Progress of construction in December 2021

As of the beginning of December, the following general construction works have been carried out on house №8:

1. Earthworks – 100%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. The frame of the building – 100%
5. Waterproofing of foundations – 100%
6. Brickwork – 100%
7. Internal engineering networks:
– Installation of ventilation shafts – 100%
– Installation of SKD – 100%
– Electrical work – 75%
– Plumbing works – 85%
– Heating – 75%
– Intercom – 90%
8. Finishing works:
– plastering of walls – 95%
– floor screeds – 75%
– plastering of ceilings – 50%
– tiling – 35%
9. Window constructions – 100%
10. Door constructions – 60%
11. Metal structures – 70%
12. Roof – 95%
13. Facade – 85%
14. Elevators – 95%
15. External engineering networks:
– power supply – 100%
– sewerage – 100%
– water supply – 100%
– gas supply – 50%
– outdoor lighting – 100%
16. Landscaping – 70%

House №9:
1. Earthworks – 85%
2. The foundation of the house – 100%
3. Tower crane foundation – 100%
4. Frame of the building – 15%
5. Waterproofing of foundations – 60%
6. Brickwork – 5%

House №14:
1. Earthworks – 65%
2. The foundation of the house – 50%
3. Tower crane foundation – 100%