Construction progress for February 2021

General construction works as of February 2, 2021:
House №8
1. Earthworks – 80% (works are underway)
2. Tower crane foundation – 100% (completed)
3. Frame of the building – 10% (work is underway)
4. Waterproofing of the bases – 50% (works are conducted)
House №7
1. Brickwork – 85% (work in progress)
2. Window constructions – 70% (works are underway)
3. Internal engineering networks
– Installation of ventilation shafts – 100% (completed)
– SKD installation – 100% (completed)
– Electrical work – 45% (work in progress)
– Plumbing works – 50% (works are underway)
– Heating – 20% (work in progress)
– Intercom – 40% (work in progress)
4. Finishing works:
– plastering of walls – 30% (works are conducted)
5. Roof – 55% (work in progress)
6. Facade – 5% (works are performed)
7. Metal structures – 30% (work is underway)
8. External engineering networks:
– power supply – 70% (works are underway)
– sewerage – 50% (works are underway)
– water supply – 50% (works are underway)