Construction progress for March 2021

General construction works as of March 2, 2021:
House №8
1. Earthworks – 80% (works are underway)
2. Frame of the building – 15% (work is underway)
3. Waterproofing of the bases – 50% (works are conducted)
4. Brickwork -5% (work is underway)
House №7
1. Window constructions – 95% (works are underway)
2. Internal engineering networks
– Installation of ventilation shafts – 100% (completed)
– SKD installation – 100% (completed)
– Electrical work – 55% (work in progress)
– Plumbing works – 60% (works are underway)
– Heating – 30% (work in progress)
– Intercom – 60% (work in progress)
3. Finishing works:
– plastering of walls – 45% (works are conducted)
4. Roof – 55% (work in progress)
5. Facade – 20% (works are underway)
6. Metal structures – 30% (work is underway)
7. Elevators – 60% (work in progress)
7. External engineering networks:
– power supply – 80% (works are underway)
– sewerage – 70% (works are underway)
– water supply – 70% (works are underway)