Installation of floor formwork above commercial premises Formwork is installed to fill the floor slab, which will become the basis between the floors. Masonry of walls in the parking lot The construction of the walls in the underground parking is carried out using high-quality materials that ensure the durability of the structure. Waterproofing of the […]
Works as of the beginning of May: House No. 14: Land improvement works – 95% (paving of sidewalks and arrangement of green areas are being completed). Shopping center: Earthworks – works on the development of the pit have been completed; Construction of the foundation is completed; Arrangement of the frame – 10% (work is being […]
Works as of the beginning of April: House No. 14: Works on the improvement of the territory – 65% (paving works on sidewalks and driveways are being carried out). Shopping center: Earthworks – works on the development of the pit have been completed; Crushed stone preparation – completed; Concrete preparation – completed; Foundation plate – […]
The “Intergal-Bud” company offers an additional discount of 2%, which can be used by military and law enforcement officers (of all branches of the military and subordination), as well as medical workers of state or communally owned institutions. The discount applies to the purchase of apartments, storage rooms or parking spaces in all residential complexes […]
Until the end of January 2024, the company “Intergal-Bud” provides the opportunity to purchase real estate at a rate below the market – 37.5 UAH per US dollar. The offer is valid for the purchase of an apartment, parking space, storage room or commercial real estate. The fixed rate applies in the case of purchase […]
As of the beginning of January 2024, general construction works on building №14: Earthworks, foundations – 100; Monolithic frame, walls and partitions – 100%; Internal engineering networks and elevators – 100%; Slot filling – 100%; Metal structures – 100%; Interior decoration and plates – 100%; Roof – 100%; Facades – 90% (painting of the facade […]
As of the beginning of December 2023, general construction works on building No. 14: Earthworks – 100%; Foundations – 100%; Monolithic frame, walls and partitions – 100%; Internal engineering networks: – arrangement of ventilation shafts and LCD – 100%; – water supply and sewerage – 95%; – heating per apartment – 90%; – electrical networks […]
As of the beginning of October 2023, general construction works on building No. 14: Earthworks – 100% Foundations – 100% Monolithic frame, walls and partitions – 100% Internal engineering networks: – arrangement of ventilation shafts and LCD – 100% -water supply and sewage – 75% – heating per apartment – 65% – electrical networks – […]